Step 10: Position Runners on Bottom as shown on
Sketch E and nail with one or two nails to hold in position. NOTE:
Do not use glue on the runners; only use 4 or 5 #9 1 ¾” screws on the
inside to hold: The Runners are only to
protect the Show Box and are not part of the Box itself.
Step 11: Place Cover #22, number side down and mark
location of Cover Front and Back Frames #5 and Cover Side Frame #6 as shown
on Sketch L. Also mark Frame Ends
where they meet. Remove Frames, coat
marked ends with glue, and nail pieces together.
|
Turn Cover #22 number side up and lay out
and mark screw locations as shown on Sketch M. After Frame glue has dried, place on Cover #22 as shown on
Sketch M. Clamp Frame to Cover to
hold in position; drill and countersink screw holes. Screw parts together using #9 1 ¾” wood
screws.
Step 12: Mark center of Cover Front Frame; locate
and install hasp. Cut molding to size (front must be 36”
long measured on inside of bevel end pieces 16” from bevel to end). And nail to frame using 2-penny
nails. Note: There is no molding on
rear of show box, and front molding must be fitted over hasp! Cut molding to size and nail to bottom of
show box. Step 13: Using Sketch N as a guide, assemble the
tray as shown. The tray can be nailed
together instead of screws but parts should be glued for greater strength. Step 14: Locate hinges and install as shown on Sketch P. Open cover and install chain at the best place to keep the cover from opening too far. |
|
|
|